— Project Summary

Queue ID
PJM-AH1-040
Capacity
150 MW
Technology
Solar
Status
active
Location
Washington, NC
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

150 MW generation in Washington, NC · In queue since June 2021 · Proposed COD July 2025

150 MW

Capacity

1

Components

Solar

4y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 1m

Schedule

9 months past proposed COD

In Study38%
Queue EntryJun 23, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-01

Project Details

State

NC

County

Washington

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Mackeys - Creswell 115 kV

Data Source

LBNL

No news available for this project.