— Project Summary

Queue ID
PJM-AH1-034
Capacity
100 MW
Technology
Solar
Status
active
Location
Barren, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

100 MW generation in Barren, KY · In queue since June 2021 · Proposed COD November 2025

100 MW

Capacity

1

Components

Solar

4y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 5m

Schedule

4 months past proposed COD

In Study38%
Queue EntryJun 14, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-15

Project Details

State

KY

County

Barren

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Patton Road Junction - Summer Shade 69 kV

Data Source

LBNL

No news available for this project.