100 MW generation in Barren, KY · In queue since June 2021 · Proposed COD November 2025
100 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 5m
Schedule
4 months past proposed COD
In Study38%
Queue EntryJun 14, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-11-15
Project Details
State
KY
County
Barren
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Patton Road Junction - Summer Shade 69 kV
Data Source
LBNL