BetaActiveSolarPJMLBNL
19.5 MW generation in Currituck, NC · In queue since June 2021 · Proposed COD August 2024
19.5 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
20 months past proposed COD
In Study38%
Queue EntryJun 14, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-08-15
Project Details
State
NC
County
Currituck
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Sligo 34.5 kV
Data Source
LBNL
No news available for this project.