— Project Summary

Queue ID
PJM-AH1-027
Capacity
25 MW
Technology
Solar
Status
active
Location
Kent, DE
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

25 MW generation in Kent, DE · In queue since May 2021 · Proposed COD June 2023

25 MW

Capacity

1

Components

Solar

4y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 1m

Schedule

34 months past proposed COD

In Study38%
Queue EntryMay 20, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-06-01

Project Details

State

DE

County

Kent

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Cartanza 230 kV

Data Source

LBNL

No news available for this project.