25 MW generation in Kent, DE · In queue since May 2021 · Proposed COD June 2023
25 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 1m
Schedule
34 months past proposed COD
In Study38%
Queue EntryMay 20, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
DE
County
Kent
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Cartanza 230 kV
Data Source
LBNL