BetaActiveSolarPJMLBNL
40 MW generation in Fayette, KY · In queue since April 2021 · Proposed COD December 2023
40 MW
Capacity
1
Components
Solar
4y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 8m
Schedule
28 months past proposed COD
In Study38%
Queue EntryApr 7, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
KY
County
Fayette
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Avon - Renaker 138 kV
Data Source
LBNL
No news available for this project.