BetaActiveBatteryPJMLBNL
80 MW storage in Rock Island, IL · In queue since March 2021 · Proposed COD October 2024
80 MW
Capacity
1
Components
Battery
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 7m
Schedule
18 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-01
Project Details
State
IL
County
Rock Island
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Cordova 345 kV
Data Source
LBNL
No news available for this project.