— Project Summary

Queue ID
PJM-AG2-655
Capacity
500 MW
Technology
Solar
Status
active
Location
Grant, WV
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

500 MW generation in Grant, WV · In queue since March 2021 · Proposed COD June 2024

500 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 3m

Schedule

21 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-30

Project Details

State

WV

County

Grant

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Mt. Storm-Bismark 500 kV

Data Source

LBNL