— Project Summary

Queue ID
PJM-AG2-646
Capacity
200 MW
Technology
Battery
Status
active
Location
Chesterfield, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

200 MW storage in Chesterfield, VA · In queue since March 2021 · Proposed COD June 2024

200 MW

Capacity

1

Components

Battery

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 3m

Schedule

22 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-10

Project Details

State

VA

County

Chesterfield

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Chesterfield 230 kV

Data Source

LBNL

No news available for this project.