BetaActiveSolarPJMLBNL
40 MW generation in Gloucester, NJ · In queue since March 2021 · Proposed COD June 2024
40 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 3m
Schedule
21 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-30
Project Details
State
NJ
County
Gloucester
Region
PJM
Developer
—
Utility
AEC
Entity
PJM
Point of Interconnection
Woodstown-High Street 69 kV
Data Source
LBNL
No news available for this project.