BetaActiveSolarPJMLBNL
20 MW generation in King And Queen, VA · In queue since March 2021 · Proposed COD November 2023
20 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 8m
Schedule
29 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-01
Project Details
State
VA
County
King And Queen
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
St. Johns - Dunbrook 34.5 kV
Data Source
LBNL
No news available for this project.