BetaActiveSolarPJMLBNL
150 MW generation in Brunswick, VA · In queue since January 2021 · Proposed COD October 2024
150 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 9m
Schedule
18 months past proposed COD
In Study38%
Queue EntryJan 29, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-01
Project Details
State
VA
County
Brunswick
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Rawlings-Clover 500 kV
Data Source
LBNL
No news available for this project.