BetaActiveBatteryPJMLBNL
100 MW storage in Brunswick, VA · In queue since March 2021 · Proposed COD March 2024
100 MW
Capacity
1
Components
Battery
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3 years
Schedule
24 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-29
Project Details
State
VA
County
Brunswick
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Brunswick Collector Bus - Wake 500 kV
Data Source
LBNL
No news available for this project.