— Project Summary

Queue ID
PJM-AG2-570
Capacity
400 MW
Technology
Solar
Status
active
Location
Brunswick, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

400 MW generation in Brunswick, VA · In queue since March 2021 · Proposed COD March 2024

400 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

24 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-03-29

Project Details

State

VA

County

Brunswick

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Brunswick Collector - Wake 500 kV

Data Source

LBNL

No news available for this project.