80 MW generation in WV · In queue since March 2021 · Proposed COD February 2024
80 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 11m
Schedule
25 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-02-25
Project Details
State
WV
County
—
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Stink Run _x0013_ Sundial 138 kV
Data Source
LBNL