— Project Summary

Queue ID
PJM-AG2-538
Capacity
20 MW
Technology
Solar+Battery
Status
active
Location
Elk, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

20 MW hybrid in Elk, PA · In queue since March 2021 · Proposed COD October 2022

20 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 7m

Schedule

42 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-15

Project Details

State

PA

County

Elk

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Ridgeway - Motion Control 46 kV

Data Source

LBNL

No news available for this project.