BetaActiveBatteryPJMLBNL
20 MW storage in Warren, NJ · In queue since March 2021 · Proposed COD August 2022
20 MW
Capacity
1
Components
Battery
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 5m
Schedule
43 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-08-31
Project Details
State
NJ
County
Warren
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Hackettstown-Pohatcong J738-1 34.5 kV II
Data Source
LBNL
No news available for this project.