— Project Summary

Queue ID
PJM-AG2-535
Capacity
20 MW
Technology
Battery
Status
active
Location
Warren, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

20 MW storage in Warren, NJ · In queue since March 2021 · Proposed COD August 2022

20 MW

Capacity

1

Components

Battery

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 5m

Schedule

43 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-08-31

Project Details

State

NJ

County

Warren

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Hackettstown-Pohatcong J738-1 34.5 kV II

Data Source

LBNL

No news available for this project.