— Project Summary

Queue ID
PJM-AG2-516
Capacity
120 MW
Technology
Solar
Status
active
Location
Winnebago, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

120 MW generation in Winnebago, IL · In queue since March 2021 · Proposed COD October 2023

120 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 7m

Schedule

29 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-10-31

Project Details

State

IL

County

Winnebago

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Pecatonica 138kV

Data Source

LBNL

No news available for this project.