100 MW generation in Lucas, OH · In queue since March 2021 · Proposed COD October 2023
100 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 7m
Schedule
29 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-31
Project Details
State
OH
County
Lucas
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Midway 345 kV III
Data Source
LBNL