BetaActiveHydroPJMLBNL
15 MW generation in Garrett, MD · In queue since March 2021 · Proposed COD December 2023
15 MW
Capacity
1
Components
Hydro
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 9m
Schedule
27 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
MD
County
Garrett
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Westvaco - Mt Zion 138 kV
Data Source
LBNL