BetaActiveSolarPJMLBNL
10.6 MW generation in Henry, IN · In queue since March 2021 · Proposed COD May 2022
10.6 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 2m
Schedule
47 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-05-31
Project Details
State
IN
County
Henry
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Madison - Tanners Creek 138 kV
Data Source
LBNL
No news available for this project.