— Project Summary

Queue ID
PJM-AG2-487
Capacity
10.6 MW
Technology
Solar
Status
active
Location
Henry, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

10.6 MW generation in Henry, IN · In queue since March 2021 · Proposed COD May 2022

10.6 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 2m

Schedule

47 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-05-31

Project Details

State

IN

County

Henry

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Madison - Tanners Creek 138 kV

Data Source

LBNL

No news available for this project.