4.1 MW generation in Northumberland, PA · In queue since March 2021 · Proposed COD July 2022
4.1 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 4m
Schedule
44 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-07-31
Project Details
State
PA
County
Northumberland
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Derry Tap-Derry Bus 69 kV III
Data Source
LBNL