BetaActiveSolarPJMLBNL
0.5 MW generation in York, PA · In queue since March 2021 · Proposed COD March 2022
0.5 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1 year
Schedule
49 months past proposed COD
In Study38%
Queue EntryMar 31, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-03-31
Project Details
State
PA
County
York
Region
PJM
Developer
—
Utility
ME
Entity
PJM
Point of Interconnection
Hokes-Jackson 69 kV IV
Data Source
LBNL
No news available for this project.