— Project Summary

Queue ID
PJM-AG2-455
Capacity
280 MW
Technology
Solar
Status
active
Location
Fountain, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

280 MW generation in Fountain, IN · In queue since March 2021 · Proposed COD March 2024

280 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

24 months past proposed COD

In Study38%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-03-31

Project Details

State

IN

County

Fountain

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Dequine - Sullivan 345 kV

Data Source

LBNL

No news available for this project.