— Project Summary

Queue ID
PJM-AG2-447
Capacity
20 MW
Technology
Solar
Status
active
Location
New Castle, DE
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

20 MW generation in New Castle, DE · In queue since March 2021 · Proposed COD February 2024

20 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 11m

Schedule

26 months past proposed COD

In Study38%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-02-01

Project Details

State

DE

County

New Castle

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Cedar Creek 138 kV VII

Data Source

LBNL

No news available for this project.