BetaActiveSolarPJMLBNL
100 MW generation in Charlotte, VA · In queue since March 2021 · Proposed COD December 2024
100 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 9m
Schedule
15 months past proposed COD
In Study38%
Queue EntryMar 30, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
VA
County
Charlotte
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Twittys Creek - Madisonville 115 kV
Data Source
LBNL
No news available for this project.