— Project Summary

Queue ID
PJM-AG2-436
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Sussex, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

400 MW hybrid in Sussex, VA · In queue since March 2021 · Proposed COD December 2023

400 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 9m

Schedule

27 months past proposed COD

In Study38%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

VA

County

Sussex

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Carson - Rogers Road 500 kV

Data Source

LBNL