— Project Summary

Queue ID
PJM-AG2-424
Capacity
63.25 MW
Technology
Solar+Battery
Status
active
Location
Larue, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

63.25 MW hybrid in Larue, KY · In queue since March 2021 · Proposed COD May 2023

63.25 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 2m

Schedule

34 months past proposed COD

In Study38%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-05-31

Project Details

State

KY

County

Larue

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Bonnieville - Lebanon 138 kV

Data Source

LBNL

No news available for this project.