— Project Summary

Queue ID
PJM-AG2-411
Capacity
63 MW
Technology
Solar
Status
active
Location
Somerset, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

63 MW generation in Somerset, PA · In queue since March 2021 · Proposed COD July 2024

63 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 4m

Schedule

21 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-01

Project Details

State

PA

County

Somerset

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Statler Hill 115 kV

Data Source

LBNL

No news available for this project.