— Project Summary

Queue ID
PJM-AG2-408
Capacity
18 MW
Technology
Solar
Status
active
Location
Allen, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

18 MW generation in Allen, IN · In queue since March 2021 · Proposed COD September 2022

18 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 6m

Schedule

42 months past proposed COD

In Study38%
Queue EntryMar 30, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-09-30

Project Details

State

IN

County

Allen

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Allen 345 kV

Data Source

LBNL

No news available for this project.