BetaActiveSolarPJMLBNL
44 MW generation in Randolph, IN · In queue since March 2021 · Proposed COD December 2021
44 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
9 months
Schedule
52 months past proposed COD
In Study38%
Queue EntryMar 30, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-15
Project Details
State
IN
County
Randolph
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Losantville 345 kV
Data Source
LBNL