— Project Summary

Queue ID
PJM-AG2-382
Capacity
70 MW
Technology
Solar
Status
active
Location
Bertie, NC
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

70 MW generation in Bertie, NC · In queue since March 2021 · Proposed COD September 2024

70 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 6m

Schedule

18 months past proposed COD

In Study38%
Queue EntryMar 29, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-20

Project Details

State

NC

County

Bertie

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Cashie 230 kV

Data Source

LBNL

No news available for this project.