20 MW generation in Clark, OH · In queue since March 2021 · Proposed COD July 2023
20 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 4m
Schedule
32 months past proposed COD
In Study38%
Queue EntryMar 29, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-07-31
Project Details
State
OH
County
Clark
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
North Hampton _x0013_ Medway 69 kV
Data Source
LBNL
No news available for this project.