— Project Summary

Queue ID
PJM-AG2-298
Capacity
60 MW
Technology
Solar
Status
active
Location
Marion, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

60 MW generation in Marion, KY · In queue since March 2021 · Proposed COD September 2024

60 MW

Capacity

1

Components

Solar

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 6m

Schedule

19 months past proposed COD

In Study38%
Queue EntryMar 23, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-01

Project Details

State

KY

County

Marion

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Loretto 69 kV

Data Source

LBNL

No news available for this project.