BetaActiveSolarPJMLBNL
20 MW generation in Washington, MD · In queue since March 2021 · Proposed COD September 2024
20 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 6m
Schedule
18 months past proposed COD
In Study38%
Queue EntryMar 22, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-30
Project Details
State
MD
County
Washington
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Hagerstown-Conservit 34.5 kV
Data Source
LBNL
No news available for this project.