— Project Summary

Queue ID
PJM-AG2-270
Capacity
150 MW
Technology
Battery
Status
active
Location
Halifax, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

150 MW storage in Halifax, VA · In queue since March 2021 · Proposed COD December 2025

150 MW

Capacity

1

Components

Battery

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 9m

Schedule

3 months past proposed COD

In Study38%
Queue EntryMar 19, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

VA

County

Halifax

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Clover 230 kV

Data Source

LBNL

No news available for this project.