— Project Summary

Queue ID
PJM-AG2-202
Capacity
20 MW
Technology
Battery
Status
active
Location
City Of Lynchburg, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

20 MW storage in City Of Lynchburg, VA · In queue since March 2021 · Proposed COD October 2022

20 MW

Capacity

1

Components

Battery

5 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 7m

Schedule

41 months past proposed COD

In Study38%
Queue EntryMar 4, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

VA

County

City Of Lynchburg

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Reusens 12.47 kV

Data Source

LBNL

No news available for this project.