— Project Summary

Queue ID
PJM-AG2-198
Capacity
80 MW
Technology
Solar
Status
active
Location
Prince Edward, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

80 MW generation in Prince Edward, VA · In queue since February 2021 · Proposed COD February 2024

80 MW

Capacity

1

Components

Solar

5y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

25 months past proposed COD

In Study38%
Queue EntryFeb 28, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-02-25

Project Details

State

VA

County

Prince Edward

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Briery-Clover 230 kV

Data Source

LBNL