— Project Summary

Queue ID
PJM-AG2-189
Capacity
19.8 MW
Technology
Solar
Status
active
Location
Warren, NJ
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

19.8 MW generation in Warren, NJ · In queue since February 2021 · Proposed COD February 2022

19.8 MW

Capacity

1

Components

Solar

5y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1 year

Schedule

50 months past proposed COD

In Study38%
Queue EntryFeb 27, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-02-23

Project Details

State

NJ

County

Warren

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Washington-Pequest River 34.5 kV

Data Source

LBNL

No news available for this project.