BetaActiveSolarPJMLBNL
13.3 MW generation in Cumberland, PA · In queue since February 2021 · Proposed COD August 2023
13.3 MW
Capacity
1
Components
Solar
5y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 6m
Schedule
32 months past proposed COD
In Study38%
Queue EntryFeb 25, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-08-18
Project Details
State
PA
County
Cumberland
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Newville-Nottingham Tap 1 69 kV
Data Source
LBNL