— Project Summary

Queue ID
PJM-AG2-166
Capacity
13.3 MW
Technology
Solar
Status
active
Location
Cumberland, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

13.3 MW generation in Cumberland, PA · In queue since February 2021 · Proposed COD August 2023

13.3 MW

Capacity

1

Components

Solar

5y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 6m

Schedule

32 months past proposed COD

In Study38%
Queue EntryFeb 25, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-08-18

Project Details

State

PA

County

Cumberland

Region

PJM

Developer

Utility

PPL

Entity

PJM

Point of Interconnection

Newville-Nottingham Tap 1 69 kV

Data Source

LBNL

No news available for this project.