— Project Summary

Queue ID
PJM-AG2-164
Capacity
270 MW
Technology
Solar
Status
active
Location
Decatur, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

270 MW generation in Decatur, IN · In queue since February 2021 · Proposed COD December 2024

270 MW

Capacity

1

Components

Solar

5y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 10m

Schedule

16 months past proposed COD

In Study38%
Queue EntryFeb 25, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-02

Project Details

State

IN

County

Decatur

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Jefferson-Greentown 765 kV

Data Source

LBNL

No news available for this project.