BetaActiveSolarBatteryPJMLBNL
250 MW hybrid in Fountain, IN · In queue since February 2021 · Proposed COD June 2024
250 MW
Capacity
1
Components
Solar
5y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 4m
Schedule
22 months past proposed COD
In Study38%
Queue EntryFeb 25, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
IN
County
Fountain
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Dequine-Eugene 345 kV
Data Source
LBNL