— Project Summary

Queue ID
PJM-AG2-159
Capacity
61 MW
Technology
Solar+Battery
Status
active
Location
Grant, KY
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

61 MW hybrid in Grant, KY · In queue since February 2021 · Proposed COD September 2023

61 MW

Capacity

1

Components

Solar

5y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 7m

Schedule

31 months past proposed COD

In Study38%
Queue EntryFeb 25, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-15

Project Details

State

KY

County

Grant

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Williamstown 69 kV

Data Source

LBNL