BetaActiveSolarPJMLBNL
150 MW generation in Pittsylvania, VA · In queue since February 2021 · Proposed COD February 2024
150 MW
Capacity
1
Components
Solar
5y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3 years
Schedule
26 months past proposed COD
In Study38%
Queue EntryFeb 23, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-02-02
Project Details
State
VA
County
Pittsylvania
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Banister-Bear Skin 138 kV
Data Source
LBNL
No news available for this project.