— Project Summary

Queue ID
PJM-AG2-150
Capacity
5.25 MW
Technology
Hydro
Status
active
Location
Allegheny, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveHydroPJMLBNL

5.25 MW generation in Allegheny, PA · In queue since February 2021 · Proposed COD December 2022

5.25 MW

Capacity

1

Components

Hydro

5y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 10m

Schedule

39 months past proposed COD

In Study38%
Queue EntryFeb 23, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

PA

County

Allegheny

Region

PJM

Developer

Utility

DL

Entity

PJM

Point of Interconnection

River Dock 23 kV

Data Source

LBNL

No news available for this project.