BetaActiveHydroPJMLBNL
5.25 MW generation in Allegheny, PA · In queue since February 2021 · Proposed COD December 2022
5.25 MW
Capacity
1
Components
Hydro
5y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 10m
Schedule
39 months past proposed COD
In Study38%
Queue EntryFeb 23, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
PA
County
Allegheny
Region
PJM
Developer
—
Utility
DL
Entity
PJM
Point of Interconnection
River Dock 23 kV
Data Source
LBNL
No news available for this project.