40 MW generation in Van Buren, MI · In queue since February 2021 · Proposed COD December 2026
40 MW
Capacity
1
Components
Solar
5y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 10m
In Study38%
Queue EntryFeb 1, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
MI
County
Van Buren
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Almena-Valley 69 kV
Data Source
LBNL