BetaActiveSolarPJMLBNL
15.44 MW generation in Preble, OH · In queue since January 2021 · Proposed COD December 2022
15.44 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 11m
Schedule
39 months past proposed COD
In Study38%
Queue EntryJan 29, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
OH
County
Preble
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Camden-Crystal 69 kV
Data Source
LBNL
No news available for this project.