— Project Summary

Queue ID
PJM-AG2-125
Capacity
15.44 MW
Technology
Solar
Status
active
Location
Preble, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

15.44 MW generation in Preble, OH · In queue since January 2021 · Proposed COD December 2022

15.44 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

1y 11m

Schedule

39 months past proposed COD

In Study38%
Queue EntryJan 29, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

OH

County

Preble

Region

PJM

Developer

Utility

Dayton

Entity

PJM

Point of Interconnection

Camden-Crystal 69 kV

Data Source

LBNL

No news available for this project.