— Project Summary

Queue ID
PJM-AG2-124
Capacity
33.34 MW
Technology
Solar
Status
active
Location
King And Queen, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

33.34 MW generation in King And Queen, VA · In queue since January 2021 · Proposed COD December 2023

33.34 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 11m

Schedule

27 months past proposed COD

In Study38%
Queue EntryJan 29, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

VA

County

King And Queen

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Shackleford-Harmony 115 kV

Data Source

LBNL

No news available for this project.