100 MW generation in Livingston, IL · In queue since January 2021 · Proposed COD March 2024
100 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
25 months past proposed COD
In Study38%
Queue EntryJan 29, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-01
Project Details
State
IL
County
Livingston
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Dresden-Pontiac Midpoint 345 kV
Data Source
LBNL