14.8 MW generation in Campbell, VA · In queue since January 2021 · Proposed COD February 2023
14.8 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 1m
Schedule
38 months past proposed COD
In Study38%
Queue EntryJan 29, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-02-06
Project Details
State
VA
County
Campbell
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Perth 34.5 kV Substation (Circuit 408)
Data Source
LBNL