— Project Summary

Queue ID
PJM-AG2-095
Capacity
18 MW
Technology
Solar
Status
active
Location
Prince George, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

18 MW generation in Prince George, VA · In queue since January 2021 · Proposed COD December 2023

18 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 11m

Schedule

28 months past proposed COD

In Study38%
Queue EntryJan 28, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-08

Project Details

State

VA

County

Prince George

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Hopewell 34.5 kV (Circuit 313)

Data Source

LBNL